So far, the Brigit’s Village project has spent over $11.3M locally for labor and materials. We have been blessed to provide work and income to local people and look forward to serving our residents. The project is ahead of schedule and we anticipate finishing the building by the end of June and hope to finish all punch work, final inspections and certificate of occupancy in July.

Construction Schedule

2024Q3 - earth work, utilities, foundations

2024Q4 - framing, roofing, start rough-in

2025Q1 - interior trades (electric, plumbing, HVAC), drywall

2025Q2 - flooring, kitchen & bathroom finishing, appliances, paint

2025Q3 (now Q2)- interior finishing, punch lists, closeout, final inspections